Angola

10.4 - Single window

Articles 10.4.110.4.210.4.310.4.4
View measure text
Indicative date of implementation 30 June 2023
Definitive date of implementation 30 June 2027
Extension of time
Request received
23 March 2023
Original definitive date
30 June 2024
New date requested
30 June 2027
Date approved
30 June 2027
Reason
Lack of donor assistance and support for capacity building required for implementation of this category C measure. Undergoing discussions with a donor partner.
Committee approval:
Approved
Link to notification
Assistance required for implementation  ICT infrastructure.
 Institutional capacity building.
 Training of personnel and awareness-raising.

Tags: Information and communication technologies (ICT), Infrastructure and equipment, Human resources and training

Donor / Agency To be determined
Progress reported To be determined

About the TFA Database