12 - Customs cooperation
|
Implementation Date |
||||||
|---|---|---|---|---|---|---|
| Article | Type | Indicative | Definitive | Deadline for extension request, if required | Additional Information | |
| 12.1 | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.1.1 | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.1.2 | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.2 | c | 31 December 2020 | 31 December 2023 |
|
TA Requirements & Progress | |
| 12.2.1 | c | 31 December 2020 | 31 December 2023 |
|
TA Requirements & Progress | |
| 12.2.2 | c | 31 December 2020 | 31 December 2023 |
|
TA Requirements & Progress | |
| 12.3 | c | 31 December 2020 | 31 December 2023 |
|
TA Requirements & Progress | |
| 12.4 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.4.1 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.4.1 (a) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.4.1 (b) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.4.1 (c) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.4.1 (d) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.4.1 (e) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.4.1 (f) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.4.2 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.1 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.1 (a) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.1 (b) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.1 (c) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.1 (d) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.1 (e) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.1 (f) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.2 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.5.3 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.6 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.6.1 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.6.1 (a) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.6.1 (b) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.6.1 (c) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.6.1 (d) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.6.1 (e) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.6.2 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.7 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.7.1 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.7.1 (a) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.7.1 (b) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.7.1 (c) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.7.1 (d) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.7.1 (e) | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.7.2 | c | 31 December 2020 | 31 December 2020 |
|
TA Requirements & Progress | |
| 12.8 | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.9 | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.9.1 | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.9.2 | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 (a) | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 (b) | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 (c) | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 (d) | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 (e) | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 (f) | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 (g) | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.10 (h) | b | 31 December 2020 | 31 December 2020 |
|
More information | |
| 12.11 |
c
B C
|
31 December 2020 |
31 December 2022
Original date: 31 December 2020 Committee approval: Approved |
New extended date
View reason
Given that this year is ending and searching for donors to support in the implementation of regional activities including participation in regional events as well as to provide relevant capacity building activities requires additional time, the Kyrgyz Republic needs to prolong the implementation of Article 12.11 to 2022
|
TA Requirements & Progress | |
| 12.11.1 |
c
B C
|
31 December 2020 |
31 December 2022
Original date: 31 December 2020 Committee approval: Approved |
New extended date
View reason
Given that this year is ending and searching for donors to support in the implementation of regional activities including participation in regional events as well as to provide relevant capacity building activities requires additional time, the Kyrgyz Republic needs to prolong the implementation of Article 12.11 to 2022
|
TA Requirements & Progress | |
| 12.11.1 (a) |
c
B C
|
31 December 2020 |
31 December 2022
Original date: 31 December 2020 Committee approval: Approved |
New extended date
View reason
Given that this year is ending and searching for donors to support in the implementation of regional activities including participation in regional events as well as to provide relevant capacity building activities requires additional time, the Kyrgyz Republic needs to prolong the implementation of Article 12.11 to 2022
|
TA Requirements & Progress | |
| 12.11.1 (b) |
c
B C
|
31 December 2020 |
31 December 2022
Original date: 31 December 2020 Committee approval: Approved |
New extended date
View reason
Given that this year is ending and searching for donors to support in the implementation of regional activities including participation in regional events as well as to provide relevant capacity building activities requires additional time, the Kyrgyz Republic needs to prolong the implementation of Article 12.11 to 2022
|
TA Requirements & Progress | |
| 12.11.1 (c) |
c
B C
|
31 December 2020 |
31 December 2022
Original date: 31 December 2020 Committee approval: Approved |
New extended date
View reason
Given that this year is ending and searching for donors to support in the implementation of regional activities including participation in regional events as well as to provide relevant capacity building activities requires additional time, the Kyrgyz Republic needs to prolong the implementation of Article 12.11 to 2022
|
TA Requirements & Progress | |
| 12.11.2 |
c
B C
|
31 December 2020 |
31 December 2022
Original date: 31 December 2020 Committee approval: Approved |
New extended date
View reason
Given that this year is ending and searching for donors to support in the implementation of regional activities including participation in regional events as well as to provide relevant capacity building activities requires additional time, the Kyrgyz Republic needs to prolong the implementation of Article 12.11 to 2022
|
TA Requirements & Progress | |
| 12.12 | c | 31 December 2020 | 31 December 2022 |
|
TA Requirements & Progress | |
| 12.12.1 | c | 31 December 2020 | 31 December 2022 |
|
TA Requirements & Progress | |
| 12.12.2 | c | 31 December 2020 | 31 December 2022 |
|
TA Requirements & Progress | |
Legend
| A | Notified in Cat. A |
| Ap | Partially notified in A |
| N | Not yet notified |
| B | Notified in Cat. B |
| Bp | Partially notified in B |
| CB | Shift from C to B |
| E | Extension of time requested |
| C | Notified in Cat. C |
| Cp | Partially notified in C |
| BC | Shift from B to C |
| Arrangements & Progress |