Tonga
7.1 - Pre-arrival processing
Articles |
7.1.1
–
7.1.2
View measure text |
---|---|
Indicative date of implementation | 22 February 2018 |
Definitive date of implementation | 31 December 2020 |
Extension of time |
Request received
19 February 2021
Original definitive date
31 December 2020
New date requested
31 December 2021
Date approved
Reason
Impact of COVID-19 on resources
Committee approval:
Not approved
Link to notification
|