8.1
View measure text |
|---|---|
| Indicative date of implementation | 31 December 2023 |
| Definitive date of implementation | 31 December 2023 |
| Extension of implementation dates |
Request received
31 August 2023
Original definitive date
31 December 2023
New date requested
30 June 2025
Agreed date
30 June 2025
Reason
Trinidad and Tobago is currently pursuing amendments to its policy framework to comply with this Article. However, it is anticipated that the reform would not be completed by the initial deadline, therefore Trinidad and Tobago is requesting additional time to implement this measure.
Committee approval:
Approved
Link to notification
|
| Articles |
8.2 (a), (b), (c), (d), (e)
View measure text |
| Indicative date of implementation | 31 December 2023 |
| Definitive date of implementation | 31 December 2023 |
| Extension of implementation dates |
Request received
31 August 2023
Original definitive date
31 December 2023
New date requested
30 June 2025
Agreed date
30 June 2025
Reason
Trinidad and Tobago is currently pursuing amendments to its policy framework to comply with this Article. However, it is anticipated that the reform would not be completed by the initial deadline, therefore Trinidad and Tobago is requesting additional time to implement this measure.
Committee approval:
Approved
Link to notification
|