| Indicative date of implementation | 31 December 2025 |
| Definitive date of implementation | 31 December 2025 |
| Extension of time |
Request received
25 November 2025
Original definitive date
31 December 2025
New date requested
31 December 2028
Date approved
Reason
Full implementation is linked to connectivity to the Single Window. Extension will facilitate connectivity of border agencies
Committee approval:
Pending
Link to notification
|
| Assistance required for implementation |
• ICT technical Infrastructure/back up and security preparedness • Develop Multi-Agency Risk Management Framework • Implement Multi-Agency Risk Management Framework on ASYCUDA World Selectivity Platform • Implement the Governance structures for Multi-Agency Risk Management framework • Capacity building on sustainable operations of Multi-Agency Risk Management Framework • Connect scanners to ASYCUDA World |
| Donor / Agency | Not yet notified |