Angola
Articles |
6.1.1
–
6.1.2
–
6.1.3
–
6.1.4
View measure text |
---|---|
Indicative date of implementation | 30 June 2021 |
Definitive date of implementation | 30 June 2026 |
Extension of time |
Request received
23 March 2023
Original definitive date
30 June 2023
New date requested
30 June 2026
Date approved
30 June 2026
Reason
Lack of donor assistance and support for capacity building required for implementation of this category C measure
Committee approval:
Approved
Link to notification
|
Assistance required for implementation |
Develop competence in the use of methodologies for quantifying costs in order to justify fees and charges. Develop a comprehensive training programme to periodically assess existing and new fees and charges. Draw up and publish a single schedule of all fees and charges related to imports and exports. |
Donor / Agency | To be determined |
Progress reported | To be determined |