Guinea
| Articles |
10.4.1
–
10.4.2
–
10.4.3
–
10.4.4
View measure text |
|---|---|
| Indicative date of implementation | 31 December 2025 |
| Definitive date of implementation | 31 December 2026 |
| Deadline for extension request, if required | 2 October 2026 |
| Extension of time |
Request received
24 September 2025
Original definitive date
31 December 2025
New date requested
31 December 2026
Date approved
31 December 2026
Reason
La Guinée a rencontré des difficultés pour mobiliser l'assistance technique et le renforcement des capacités nécessaires, et un délai supplémentaire est nécessaire pour mettre en œuvre cette mesure.
Committee approval:
Approved
Link to notification
|
| Assistance required for implementation |
• Creating a legal and regulatory framework for implementing the Single Window for Foreign Trade. • Installing IT equipment. |
| Donor / Agency | Not yet notified |
| Progress reported | Not yet notified |