Solomon Islands
| Articles |
7.6.1
–
7.6.2
View measure text |
|---|---|
| Indicative date of implementation | 22 February 2022 |
| Definitive date of implementation | 31 December 2036 |
| Deadline for extension request, if required | 2 October 2036 |
| Assistance required for implementation |
• Regulatory Framework: To enable the monitoring and measurement of performance. • Human Resources and Training: Support to publish release times and other necessary information to comply with this article. |
| Donor / Agency |
Australia |
| Progress reported |
22 August 2022
—
G/TFA/N/SLB/2
Solomon Islands conducted TRS in August 2016, one year after introduction of the ASYCUDA system in June 2015. This was the only time TRS was carried out in the country.Solomon Islands needs further support on: • Regulatory Framework: To establish formal Policy/Procedures to implement the TRS and its results on regular basis • Human Resource and Training: Need to train certain identified staff to take up responsibility for the task trained in design, implementation and analysis of a TRS. |