Zambia
| Articles |
11.1 (a), (b)
View measure text |
|---|---|
| Indicative date of implementation | 31 December 2025 |
| Definitive date of implementation | 31 December 2025 |
| Extension of time |
Request received
25 November 2025
Original definitive date
31 December 2025
New date requested
31 December 2028
Date approved
Reason
To facilitate the creation of smart corridors and the procurement, deployment and implementation of the electronic cargo tracking system
Committee approval:
Pending
Link to notification
|
| Shift | Shift from Cat. B to Cat. C notification. |
| Assistance required for implementation |
• Implementation of electronic exchange of data with other Customs administrations • Implementation of Electronic Cargo Tracking System (ECTS) within Zambia • Implementation of Electronic Cargo Tracking System along corridors • Implementation of Regional Transit Guarantee Scheme • Stakeholder education on transit procedures and controls |
| Donor / Agency | Not yet notified |
| Progress reported | Not yet notified |
| Articles |
11.2
View measure text |
| Indicative date of implementation | 31 December 2025 |
| Definitive date of implementation | 31 December 2025 |
| Extension of time |
Request received
25 November 2025
Original definitive date
31 December 2025
New date requested
31 December 2028
Date approved
Reason
To facilitate the creation of smart corridors and the procurement, deployment and implementation of the electronic cargo tracking system
Committee approval:
Pending
Link to notification
|
| Shift | Shift from Cat. B to Cat. C notification. |
| Assistance required for implementation |
• Implementation of electronic exchange of data with other Customs administrations • Implementation of Electronic Cargo Tracking System (ECTS) within Zambia • Implementation of Electronic Cargo Tracking System along corridors • Implementation of Regional Transit Guarantee Scheme • Stakeholder education on transit procedures and controls |
| Donor / Agency | Not yet notified |
| Progress reported | Not yet notified |
| Articles |
11.3
View measure text |
| Indicative date of implementation | 31 December 2025 |
| Definitive date of implementation | 31 December 2025 |
| Extension of time |
Request received
25 November 2025
Original definitive date
31 December 2025
New date requested
31 December 2028
Date approved
Reason
To facilitate the creation of smart corridors and the procurement, deployment and implementation of the electronic cargo tracking system
Committee approval:
Pending
Link to notification
|
| Shift | Shift from Cat. B to Cat. C notification. |
| Assistance required for implementation |
• Implementation of electronic exchange of data with other Customs administrations • Implementation of Electronic Cargo Tracking System (ECTS) within Zambia • Implementation of Electronic Cargo Tracking System along corridors • Implementation of Regional Transit Guarantee Scheme • Stakeholder education on transit procedures and controls |
| Donor / Agency | Not yet notified |
| Progress reported | Not yet notified |
| Articles |
11.7
–
11.8
–
11.9
–
11.10
–
11.11
–
11.12
–
11.13
–
11.14
–
11.15
–
11.16 (a), (b), (c)
–
11.17
View measure text |
| Indicative date of implementation | 31 December 2030 |
| Definitive date of implementation | 31 December 2030 |
| Deadline for extension request, if required | 2 October 2030 |
| Extension of time |
Request received
25 November 2025
Original definitive date
31 December 2025
New date requested
31 December 2028
Date approved
Reason
To facilitate the creation of smart corridors and the procurement, deployment and implementation of the electronic cargo tracking system
Committee approval:
Pending
Link to notification
|
| Assistance required for implementation |
• Implementation of electronic exchange of data with other Customs administration • Implementation of Electronic Cargo Tracking System (ECTS) within Zambia • Implementation of ECTS along corridors • Implementation of Regional Transit Guarantee Scheme • Stakeholder education on transit procedures and controls |
| Donor / Agency | Not yet notified |
| Progress reported | Not yet notified |