Cambodia
Articles |
11.5
View measure text |
---|---|
Indicative date of implementation | 31 December 2022 |
Definitive date of implementation | 31 December 2025 |
Assistance required for implementation | • TACB is needed for expanding road and establishing lane separation. |
Donor / Agency |
Asian Development Bank |
Progress reported |
22 August 2022 — G/TFA/N/KHM/4/Rev.1Progress in the provision of technical assistance and capacity building support:Cambodia has fully implemented most provisions of Article 11 on Freedom of Transit, to mention provisions 11.4, 11.6 to 11.17 being designated in category A. However, the provision 11.5 is about the encouragement of the physically separate infrastructures such as lanes, berths and similar for traffic in transit is not yet fully implemented and seeking for financial and technical assistance from development partners. At the 2nd NCTF meeting on 19 July 2022, ADB expressed their interest to provide assistance for the implementation of this provision. 19 February 2021 — G/TFA/N/KHM/4Progress in the provision of technical assistance and capacity building support:To be determined TACB support needs include: The physically separate infrastructure such as lanes, berths and similar for traffic in transit is limited and need financial and technical assistance to fully implement this provision. |