Cambodge

11 - Transit

Articles 11.5
Texte de la mesure
Date indicative de mise en oeuvre 31 décembre 2022
Date définitive de mise en oeuvre 31 décembre 2025
Assistance requise pour la mise en oeuvre • Besoin d'ATRC pour l'élargissement des routes et la mise en place d'une séparation des voies.

Étiquettes: Infrastructure et equipment

Donateur / Agence

Banque asiatique de développement (BAD)

Progrès rapporté
22 août 2022 — G/TFA/N/KHM/4/Rev.1  
Progress in the provision of technical assistance and capacity building support:

Cambodia has fully implemented most provisions of Article 11 on Freedom of Transit, to mention provisions 11.4, 11.6 to 11.17 being designated in category A. However, the provision 11.5 is about the encouragement of the physically separate infrastructures such as lanes, berths and similar for traffic in transit is not yet fully implemented and seeking for financial and technical assistance from development partners.

At the 2nd NCTF meeting on 19 July 2022, ADB expressed their interest to provide assistance for the implementation of this provision.

19 février 2021 — G/TFA/N/KHM/4  
Progress in the provision of technical assistance and capacity building support:

To be determined

TACB support needs include:
The physically separate infrastructure such as lanes, berths and similar for traffic in transit is limited and need financial and technical assistance to fully implement this provision.
Feedback